LK Kamenné stavby

Stone wine cellar in Novosedly

Reconstruction of a wine cellar in Novosedly in Moravia using stone. Load-bearing cladding walls were created. Stone wine beams were built in the lower part of the cellar.

Kamenný vinný sklep - pohled na lisovnu
33 tons of stones were used
The construction lasted 6 months
High quality stone
Possibility of personal inspection

Reconstruction of the upper part of the cellar

  • Complete evacuation of the original cellar, including doors and stairs. Removal of the top layer of soil due to the space for leveling the substrate. Removing the surface layer of the wall.
  • Cancellation of the original electrical network.
  • Leveling and concreting the floor.
  • Establishment of a completely new electrical network and waste.
  • Area of the whole room according to the prepared design.
  • Foundation of walls, sinks and construction of stairs.
  • Exhibition of chimneys and landings for stoves.
  • After completion of all elements, subsequent laying of the floor.

Reconstruction of the lower part of the cellar

  • Complete emptying of the original cellar and removal of the top layer of soil due to the space for leveling the substrate.
  • Measurement of the construction of the canteen and subsequent introduction of the material.
  • Construction of a stone structure according to the area.
  • Weighing gravel as a base for the floor.
  • Area and subsequent laying of the floor (quality concrete mixture as a perfect imitation of wood).